A PCBA shop pulls a BOM for a new build and finds that three line items are flagged as end-of-life or stuck on a 20+ week lead time. The design hasn't changed, but the parts list no longer matches what's actually buyable. Someone on the assembly side now has to decide how to propose alternates without quietly introducing a problem the customer didn't sign off on.
This comes up more often than people outside manufacturing expect. Component shortages, obsolescence notices, and vendor allocation shifts hit boards long after the schematic is frozen. The assembly house usually sees the gap first, since they're the ones placing the purchase order, not the design team. The question is what a reasonable approval request should actually contain before it goes back to the customer or procurement contact.
At minimum it seems to need the original part number and the proposed substitute side by side, with the specific parameters that matter for that position, footprint, electrical tolerance, thermal rating, or RoHS/AEC-Q qualification depending on the application. For anything going into an automotive or medical build, that documentation probably needs to reference the relevant IPC class or qualification standard the board is being built to, since a substitution that's fine for a consumer product may not clear a Class 3 requirement.
The harder part is sequencing. Some shops batch substitution requests and wait for a single sign-off before placement, which slows the build but avoids rework. Others get verbal approval and proceed, documenting it after the fact. Both approaches carry different risks depending on how far along the order already is and how much slack the lead time allows.
For anyone who's set up or received one of these requests, what did the approval record actually need to include before procurement or engineering would sign off, and did that change based on whether the part was functionally equivalent or just form-fit compatible?