r/StructuralEngineering • u/donotdisturb898 • 8h ago
Masonry Design Cmu wall modular length question. Mason please chime in.
For some context, this is California seismic category d.
I am aware that you want your cmu wall building plan dimensions in 8” increments. Not only for constructibility & efficiency but also allow the rebar to fit adjacent to openings. But I’m doing a building expansion with a seismic gap to the existing building and the architect wants to align the opening in the new building with the opening in the existing building. But the existing building was built in the 70s and they didn’t have modular length at the opening.
My question to all:
Do you oversize the opening in the new building and do some sort of metal stud infill so the dimensions are in modular length. And the distance from end of wall to the edge of opening is in modular length?
How does a mason do non-modular cmu length and still fit the rebar in, and is it really feasible? Or is it just a labor intensive task?
4
u/ErectionEngineering 7h ago
You can cut blocks with a masonry saw. It’s just inconvenient and should be avoided when possible.
Sounds like one of those cases where it’s not possible.
2
u/Riogan_42 7h ago
Draw wall. Mason build. The end.
1
u/hookes_plasticity P.E. 7h ago
I had a building just like this two years ago. Existing building was built in the 50s and that door was definitely not on module at all. We basically just matched the location and had the contractor cut the block as required to fit. As far as rebar is concerned they will figure it out in shops to get enough bars to meet your min requirements and then get enough extra to match your opening jamb detail. It’s not too big a deal since it’ll be an interior wall anyway. Your exterior walls can still be on module. From an architectural perspective we also did not get pushback because everything ended up being furred out so them cutting partial block was not a big deal from an aesthetic point of view.
EDIT: mason might bitch and moan but that’s their problem. You need to match the existing door location.