r/datacenter • u/Elegance_1 • 18h ago
how far into bring-up do you usually find out the patching doesn't match the plan?
heard a story this week about a new build where the network folks never set foot on site, the contractor patched everything off the drawings, and it took months of troubleshooting before anyone worked out the patch panels were wrong. not a day or two of slip, weeks.
the contractor was on fixed price so in theory they eat the rework, but someone on the owner side still has to check it, and nobody wants to trace thousands of fibres by hand at the end of the job.
and the later it gets caught the worse it is, because by then everything else is stacked on top of it.
on your builds, who actually verifies the rack to rack patching before handover, and how much of it do they check? every link, a sample, or just whatever lights up?