r/softwaredevelopment • u/ClickOk5811 • 6h ago
Little's Law in 3 numbers: why "start more things" usually makes each one slower
A back-of-the-envelope tool I find useful when a team is "busy but nothing finishes".
Little's Law says that, for a stable process, on average:
Average cycle time = Work in progress ÷ Throughput
You only need three numbers, all easy to get from a board:
- WIP: how many items are in progress right now (not done, not waiting in the backlog)
- Throughput: how many items finish per week, on average
- Cycle time: how long an item takes from start to done, on average
An example with made-up numbers:
- Throughput: 5 items per week
- WIP: 20 items in progress, so average cycle time = 20 ÷ 5 = 4 weeks
- Same team, same throughput, but WIP limited to 10, so 10 ÷ 5 = 2 weeks
Nothing about the team got faster. But if throughput stays at 5 per week, half the work in progress means each item finishes in about half the time on average. And items waiting in "in progress" aren't delivering value or feedback yet.
The catch, because the formula is easy to misuse:
- It's about averages in a reasonably stable system. It doesn't predict how long one particular item will take.
- It assumes throughput doesn't change when WIP changes. In practice, too little WIP can starve people, and too much adds context switching, so throughput may move. The numbers above are an illustration, not a result.
- The "WIP" you count has to be honest. If items sit in a column called "In progress" but nobody's working on them, they still count.
- If your items vary a lot in size, the averages can hide a lot.
What I find useful is the conversation it starts: "we have 20 things in progress and finish 5 a week, so the average item is in flight for about 4 weeks. Is that OK?"
For people who've used WIP limits: how did you pick the first number? Did throughput hold up, or did people just find other ways to be busy? And where did the math not match reality?