r/PowerSystemsEE • u/ajinajing • 5h ago
How we stopped losing scope-of-work fights on site: the 1-page numbered Claim Sheet
On overseas EPC projects, the worst money losses rarely come from bad engineering — they come from "verbal site instructions" that turn into "that was always in your scope" six months later.
What actually saved us across 100+ extra items (numbered #110 to #210): we banned verbal work without a same-day, 1-page numbered Claim Sheet listing who instructed it, date, scope, and rough quantity — plus a simple yes/no scope query (e.g., "fire-stopping the GIS wall penetrations is ours, brick infill is Owner's — please confirm").
No acknowledgement receipt = it never happened. How do your teams lock down gray-area scope on site before closing the work?